10/23 Retention pond 10/23 Mobilization 10/29 Pond grading 10/29 Field report review 10/29 Dump truck on site 10/29 Temp office 10/29 Site prep underway 11/2 Site construction sign installed 11/3 seeded and straw 11/4 Foundation excavation undeway 11/4 Foundation layout and excavation 11/4 Temp facilities on site. 11/4 Retention Pond 11/9 COVID 19 screening protocols underway 11/9 Facing west 11/9 Foundation footings excavation 11/9 Unforeseen condition- short length of existing A/C piping at tie in valve 11/9 New gravel for site controls. 11/9 Facing SW. Note existing pump house which will be decommissioned and demolished as part of the project. 11/12 Gravel and compaction 11/12 Pipinga stub outs below slab/foundation in place. 11/20 Concrete forms in place 11/20 Form work in place 11/20 Facing North 11/20 Facing South 11/27 Rebar for footings/stem walls on site. 12/4 Footings poured, stem walls form work underway. 12/4 12/4 12/4 12/11 Facing South 12/11 Stem walls poured 12/11 Facing NE. 12/11 12/11 12/11 Pond seeding sprouted and growing 12/11 Facing West- towards road 12/11 Facing East 12/15 Below slab electrical conduit rough in underway 12/15 In slab floor drains and trenching to pond underway 12/15 12/15 12/15 Electrical subcontractor on site, routing below slab conduit and pulling temp power. 12/22 Gravel and rebar- ready for slab pour 12/22 12/22 Housekeeping pad formed up Floor drains routed to pond 12/22 Awaiting concrete- testing lab on site 12/22 pour and test cylinders underway 12/22 12/22 Pour begins 12/22 12/24 Slab completed and covered for cure 12/24 12/24 1/2/2021 Facing South 1/2 Filter assembly in place. 1/2 1/2 1/2 Trusses on site 1/7 Masons scaffolding erected and block work underway 1/7 Facing NE 1/7 1/7 1/7 1/7 1/10 1/10 1/10 1/17 1/17 1/17 1/17 Interior 1/17 1/22 1/22 1/22 1/22 1/22 1/22 Interior 1/22 1/22 1/22 1/22 1/22 1/30 1/30 1/30 1/30 1/30 2/6 2/6 2/6 2/6 2/21 2/21 2/21 2/21 2/21 2/21 2/21 2/21 2/21 2/21 2/21 2/21 2/21 2/21 2/21 3/7 3/7 3/7 3/7 3/7 3/7 3/7 3/7 3/7 3/7 3/7 3/7 3/7 3/7 3/7 3/7 3/12 3/12 3/12 Temp bypass/routing from well house to isolation valve downstream from future filtration plant, 3/12 3/12 3/17 concrete form for walkway between filter and chlorine rooms 3/17 3/17 3/17 3/17 Temp bypass on the existing well and access for new piping/ routing to filter building. 3/17 3/18 early AM check of pressure test. Steady at 150 psi 3/18 3/18 Power washer used to charge the system- new pipe. Isolation valves from distribution. 3/18 3/18 3/18 Concrete grade rings poured 3/18 concrete walkway poured 3/18 Duckbill and reducer to back-water discharge. 4/04 4/04 4/04 4/04 4/04 4/04 4/04 4/04 4/04 4/04 4/04 4/04 4/04 4/04 4/04 4/04 4/04 4/04 4/04 4/04 4/04 4/04 4/04 4/04 4/04 4/04 4/12 4/24 4/24 4/24 4/24 4/24 4/24 4/24 ,4/24 4/24 5/20 5/20 5/20 5/20 5/20 Temp critter proofing until demolition 5/20 5/20 5/20 5/20 5/20
Project activities update for the week ending:
10/23/2020 Site survey, retention pond, erosion controls, equipment mobilization.
10/30/2020 Retention pond grading, mobilization, site prep, foundation staking, and erosion controls underway.
11/6/2020 Pond seeded and has straw down for erosion control, foundation grade beams excavated, construction sign up, final trailer mobilization for site presence, temp driveway/gravel for mud control, and form materials being staged. COVID 19 and site safety protocols implemented. King County building inspector was to meet on 11/5 with contractor in advance of rebar install.
11/12/2020 Gravel installed and compacted, per design, for footings completed. Ready for compaction testing.
11/20/2020 Concrete forms in place. Awaiting rebar install.
12/4/2020 Footings poured, stem wall form work and rebar tie in underway. Below grade piping utility rough-in/pathway underway.
12/11/2020 Stem walls cast, ready for below slab MEP rough in and slab pour. Pond grass seed has sprouted.
12/24 Floor drains, below slab rough in completed, slab poured- awaiting filtration assembly to be placed 12/29.
12/30 Filtration assembly moved from DWA office/building up to well site and placed on slab. Building prepped for cement brick work- masons begin on 1/4/2021.
1/8/2021 Cement block install ongoing. Block and grout work to complete the week of 1/11.
1/17 Grouting up to top course completed, awaiting gable blocks and trusses set week of 1/18.
1/22 Block work/grout completed and trusses set.
1/30 Roof sheathing completed and soffits framed. Awaiting roofing.
2/6 Standing seam metal roof installation underway. Soffit board/trim installed, caulked.
2/21 Roof and gutters/down spouts complete. Interior ceiling, attic insulation complete. Wall and ceiling finish paint complete. Piping/fittings/valves to filter assembly underway.
3/7 Project has progressed into mechanical, electrical and plumbing activities.
3/19 S&B was on site for cellular signal mapping between springs and well. Below grade piping completed, system charged to test- held at 150 psi. Final concrete pour for walkways and grade rings/pads completed.